Project News: Phase II Expansion Project of 1*330 MW Thermal Power Plant, Uong Bi Vietnam

Time:2012-3-22 14:25:47

The EPC Contract of Phase II Expansion Project of 1*330 MW Thermal Power Plant, Uong Bi Vietnam was signed in Uong Bi City of Vietnam on April 11, 2008. Uong Bi Thermal Power Plant is the contract client and the finally owner of itself.
The capacity of the project is one set of 330 MW thermal power generators. The Project EPC Contract was put into effect on May 4, 2008.
Project Progress:

May 9, 2008 - ject group was dispatched to the job site
May 23, 2008 - commencement ceremony of the project
At the end of June 2008 - project kick off meeting in Chengdu
July 2008 - st review meeting in the task force office in Longquan District
August 2008 - ond review meeting in the task force office in Longquan District
Dec. 26, 2008 - st pilling ceremony at the job site
At the end of Dec. 2008, the general progress of the project was 19.8%, including: E - 3%, P - 7% and C - 2.5%.


Domestic Sales Dept: Rusheng Yu, Tel:0086 28 65530503,0086 13708186819, E-mail: Yurusheng@chengda.com;
International Business Yifan Zhao,Tel:0086 28 65530574,0086 13551820036, Fax:0086 28 65531191,E-mail:zhaoyifan@chengda.com;
President Office: Jian Feng,Tel:0086 28 65530808,0086 13679030214,E-mail: FengJian@chengda.com;